CIP Award Implementation and Timeline

 

The Wasatch Hollow Access and Amenity Improvement Project, submitted by Council Chairman Dodd and amended by Meg Roberts, was funded by the City Council. Included in the request are additional park benches, a dog fountain and multiple new access points to the park including an access point and pedestrian bridge across the creek off Rosecrest Dr. 

The Wasatch Hollow access improvements are a large project that will take time to design and construct with a tentative timeline to complete the project by the end of 2020.  SLC Public Lands is currently working with their Engineering office to speed the timeline for the benches and dog fountain.  

Further updates to the project will be posted here and on our Facebook page.

If you'd like to view the complete CIP application, as approved, click here for the pdf version.